Long term planning

Yarra’s 2025/26 states that a road seal (the thin layer of asphalt on top of the road base) lasts about 26 years:

Image source: Annual Report 2025/26.

Yarra’s website states that council manages 225 km of roads (excluding laneways), which aligns with the Road Management Plan 2025. If a newly re-sealed surface lasts 26 years, then council needs to renew about 9 km of road per year.

Image source: Yarra website.

However, Yarra is only re-sheeting (or re-sealing) 4.3 – 5.5 km per year, about half the speed it needs to be. That estimate was derived by analysing a decade’s worth of previous budgets.

Image credit: Streets Alive Yarra.

Readers can check the streets budgeted for renewal in each year on this map, which was generated using Claude AI (so it may contain some errors):

Image credit: Streets Alive Yarra.

Long term planning

The mismatch between depreciation period and renewal rate suggests that council should conduct long term planning. For example:

  • publish a map that splits all council roads up into segments
  • publish meta-data for each segment, including:
    • the date it was last re-sheeted, e.g. 2012
    • how much traffic it carries, e.g. 15,000 vehicles per day
    • how long it is expected to last, e.g. 20 years
    • the date it is planned for renewal, e.g. 2032
  • publish the planned expenditure each year for the next 30 years
    • which streets will be renewed each year, and the approximate cost for that year
    • identify any ‘peaks’ and either bring forward or delay some renewals to smooth them out

Ideally, such long term planning should include collaboration with utilities (water, gas, electricity, telecoms) who also sometimes need to dig up our roads.

More traffic = shorter lifetime

Importantly, such planning would highlight the link between traffic volume and road degradation, pointing out the value of reducing through traffic (or rat running) on council roads.

If traffic volumes on local streets can be reduced by keeping through traffic on state government arterials (so local streets provide access to residents and their visitors), then council roads will last longer and road renewal costs will be reduced.

Corridor planning

Even better, council should leverage long term planning to conduct corridor planning:

  • identify ‘corridors’, i.e. groups of streets, that could deliver a longer cycleway through the municipality, or a group of streets within a neighbourhood that could be revised to reduce rat running
  • schedule the renewals along the corridor to occur at the same time
  • design, consult, and approve the corridor treatment in the years leading up to the scheduled renewal

Complete Streets

A long-term corridor-planning approach would align with council’s resolution to consider a Complete Streets approach, from 9 June 2026:

  • a proactive, place-based and holistic approach
  • integrated with streetscape capital works planning and delivery
  • planning for areas experiencing growth and change
Complete Streets approach. Source: Minutes from 9 June 2026.

Reduced total costs

The expected outcome would be a reduction in total costs, because street improvement works could leverage the existing budget for road renewal works.

Conclusion

Streets Alive Yarra urges the City of Yarra to adopt a long-term corridor-planning approach, supporting Complete Streets, including the publication of maps and data to allow residents to see how expenditure is planned and managed.